Monday, April 20, 2009

April 20, 2009


Driveway all smooth and leveled.




All leveled and at the right height, getting preps for the slab to go down.

Friday, April 17, 2009

April 18, 2009

Earthworks and levels continue - view from the main bedroom. The 3 sheds should be blocked by the house leaving only treetops.



Moving more dirt for the 1.4m tall retaining walls. The flat level above still need to be raised 200mm and then the slab should be another 200mm from that.

April 12, 2009

House stringlines up - looking down and main dining / kitchen and lounge


Looking down from top corner of the block at 3rd bedroom / office and then Ella's bedroom and decks that split the house.
Standing on deck looking at where the first rammed earth wall will be. Ella's bedroom will overlook this and get good views.

Thursday, April 9, 2009

April 9, 2009

Looking down from the top corner of the block. Over the shed there is views in the distance.


Magpie standing where the kitchen on the floor level will be.






My dog Harley's tennis ball. Art direction - Ella Riggs

April 8, 2009


April 4, 2009


Driveway retaining wall

26m long x 1.4 meters tall.
Concrete sleepers and steel posts.


Pulling the fence down in the rain


String lining the fence and holes


It's a big hole, seriously you could of buried people in there it was that deep


My daughter Ella with the guys laying sleepers in the background for the driveway


And it is done, just the AG drain and some gravel, this was done at xmas 2008